If a project takes 6 workers 10 days to complete, how many days would it take 4 workers to complete the same project, assuming equal work rates?

Correct answer

A. 15 days

Explanation

Total work = 6 workers × 10 days = 60 worker-days. With 4 workers: 60 ÷ 4 = 15 days.