If a project takes 6 workers 10 days to complete, how many days would it take 4 workers to complete the same project, assuming equal work rates?
Difficulty: Medium
About this MCQ
Medium GMAT item. Correct choice: A. 15 days.
- A. 15 days ✓
- B. 12 days
Why not B: “12 days” is not 15 days.
- C. 8 days
Why not C: “8 days” is not 15 days.
- D. 20 days
Why not D: “20 days” is not 15 days.
Correct answer
A. 15 days
Explanation
15 days (option A) is the accepted answer to “If a project takes 6 workers 10 days to complete, how many days would it take 4 workers to complete the same project, assuming equal work rates”. Option B (12 days) is a different value from 15 days. Option C (8 days) is a different value from 15 days. Option D (20 days) is a different value from 15 days. Keep 15 days as the GMAT fact for this stem.
Source: Original practice question, MCQsHub
Tags: American Exams, Word Problems, Quant, GMAT
Submitted by: MCQsHub Editorial
Related MCQs
- If the ratio of a company's expenses to revenue is 3:5 and expenses are 0,000, what is the revenue?
- Which of the following, if true, would most weaken the argument that the new software update improved employee...
- If x is an integer and 2x + 3 is odd, which of the following must be true about x?
- Which revision best corrects the sentence: "The manager, along with her team members, were preparing the repor...
- A company's profit is calculated as revenue minus costs. If revenue is 0,000 and profit margin is 20%, what...
- Which assumption is necessary for the argument: "Since the new store location has more foot traffic, it will g...