If 9 workers can complete a project in 8 days, how many days would it take 3 workers, assuming equal work rates?
Difficulty: Medium
About this MCQ
Medium GMAT item. Correct choice: C. 24.
- A. 8
Why not A: “8” is not 24.
- B. 22
Why not B: “22” is not 24.
- C. 24 ✓
- D. 26
Why not D: “26” is not 24.
Correct answer
C. 24
Explanation
24 (option C) is the accepted answer to “If 9 workers can complete a project in 8 days, how many days would it take 3 workers, assuming equal work rates”. Option A (8) is a different value from 24. Option B (22) is a different value from 24. Option D (26) is a different value from 24. Keep 24 as the GMAT fact for this stem.
Source: Original practice question, MCQsHub
Tags: American Exams, Word Problems, Quant, GMAT
Submitted by: MCQsHub Editorial
Related MCQs
- If 5x + 3 = -27, what is the value of x?
- A value starts at 150. It increases by 25%, then decreases by 10%. What is the final value?
- A company's profit margin is 20% of its 0,000 revenue. What are the total costs?
- A company's profit margin is 40% of its 0,000 revenue. What are the total costs?
- What is 10% of 240?
- If 6x + 7 = 25, what is the value of x?