Skip to content

GMAT

If 9 workers can complete a project in 8 days, how many days would it take 3 workers, assuming equal work rates?

Difficulty: Medium

About this MCQ

Medium GMAT item. Correct choice: C. 24.

Correct answer

C. 24

Explanation

24 (option C) is the accepted answer to “If 9 workers can complete a project in 8 days, how many days would it take 3 workers, assuming equal work rates”. Option A (8) is a different value from 24. Option B (22) is a different value from 24. Option D (26) is a different value from 24. Keep 24 as the GMAT fact for this stem.

Source: Original practice question, MCQsHub

Tags: American Exams, Word Problems, Quant, GMAT

Submitted by: MCQsHub Editorial

Related MCQs

More GMAT MCQs