If 9 workers can complete a project in 20 days, how many days would it take 4 workers, assuming equal work rates?

Correct answer

C. 45

Explanation

Total work = 9 workers × 20 days = 180 worker-days. With 4 workers: 180 ÷ 4 = 45 days.