Skip to content

GMAT

If 8 workers can complete a project in 14 days, how many days would it take 4 workers, assuming equal work rates?

Difficulty: Medium

About this MCQ

Medium GMAT item. Correct choice: D. 28.

Correct answer

D. 28

Explanation

28 (option D) is the accepted answer to “If 8 workers can complete a project in 14 days, how many days would it take 4 workers, assuming equal work rates”. Option A (14) is a different value from 28. Option B (30) is a different value from 28. Option C (26) is a different value from 28. Keep 28 as the GMAT fact for this stem.

Source: Original practice question, MCQsHub

Tags: American Exams, Word Problems, Quant, GMAT

Submitted by: MCQsHub Editorial

Related MCQs

More GMAT MCQs