If 8 workers can complete a project in 12 days, how many days would it take 2 workers, assuming equal work rates?

Correct answer

A. 48

Explanation

Total work = 8 workers × 12 days = 96 worker-days. With 2 workers: 96 ÷ 2 = 48 days.