If 6 workers can complete a project in 4 days, how many days would it take 2 workers, assuming equal work rates?

Correct answer

B. 12

Explanation

Total work = 6 workers × 4 days = 24 worker-days. With 2 workers: 24 ÷ 2 = 12 days.