If 10 workers can complete a project in 14 days, how many days would it take 4 workers, assuming equal work rates?

Correct answer

A. 35

Explanation

Total work = 10 workers × 14 days = 140 worker-days. With 4 workers: 140 ÷ 4 = 35 days.