If 10 workers can complete a project in 14 days, how many days would it take 4 workers, assuming equal work rates?
Difficulty: Medium
- A. 35 ✓
- B. 14
- C. 37
- D. 33
Correct answer
A. 35
Correct answer
Source: Original practice question, MCQsHub